单项选择题

All of the following are characteristics of parametric estimating EXCEPT______.

A.Historical information
B.Quantifiable
C.Scalable
D.Activity lists
<上一题 目录 下一题>
热门 试题

单项选择题
The organization of the project is very important for successful implementation. Which factor does not have an impact of design of the project organization
A.Environmental force
B.Schedule limitation
C.Strategic choice
D.Technological factor
单项选择题
Which information is NOT found in the project charter
A.High-level project description or product requirement
B.Summary milestone schedul
C.Stakeholder influence
D.Assign project manager and type of project organizatio