单项选择题

缩短工期节约的固定费用的计算公式是( )。

A.G<SUB>j</SUB>=B<SUB>j</SUB>(1-T<SUB>j</SUB>/T<SUB>o</SUB>)
B.G<SUB>j</SUB>=f<SUB>j</SUB>(下标)(1-T<SUB>j</SUB>/T<SUB>0</SUB>)
C.G<SUB>j</SUB>=L<SUB>j</SUB>(T<SUB>0</SUB>-T<SUB>j</SUB>)
D.G<SUB>j</SUB>=Q<SUB>j</SUB>/[M<SUB>j</SUB>(1+a<SUB>j</SUB>)]