单项选择题
A generally accepted method to confirm accuracy of task progress is through ______ .
A) earned value
B) probability vs. outcome
C) maximum ceiling
D) work breakdown structure
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
A recommended corrective action is an output of which cost management process area
A) Resource planning.
B) Cost estimating.
C) Cost budgeting.
D) Cost control.
点击查看答案&解析
单项选择题
In the earned value technique, cost variance is computed as ______ .
A) EV minus PV
B) EV minus AC
C) AC minus EV
D) PV minus EV
点击查看答案&解析