单项选择题

Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.

A.milestone
B.baseline
C.quality
D.work
<上一题 目录 下一题>
热门 试题

单项选择题
The Estimate Activity Resource process is closely coordinated with the (73)process.
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
单项选择题
Project work packages are typically decomposed into smaller components called activities to provide a basis for (72), scheduling, executing, and monitoring and controlling the project work.
A.reviewing
B.estimating
C.auditing
D.expecting