Completion of project scope activities is not measured against the ______ .
A.scope statement
B.requirements
C.WBS dictionary
D.WBS
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
The causes of variances and the reasoning behind the corrective action chosen are summarized the ______ .
A.work breakdown structure
B.accounting codes for the activities
C.lessons learned
D.performance reports
点击查看答案&解析
单项选择题
In your project, you use product analysis to translating project objectives into tangible deliverables and requirements. All the following tools are used for product analysis EXCEPT ______ .
A.value engineering
B.value analysis
C.product breakdown
D.benefit/cost analysis