All of the following represent, or result from, the primary benefit of meeting quality requirements EXCEPT ______ .

A.less rework
B.higher productivity
C.lower costs
D.fewer change orders
<上一题 目录 下一题>
热门 试题

单项选择题
After project control, organizational process assets are updated. Wherever checklists are used, the completed checklists should become part of the ______ .
A.project's records
B.project files
C.project quality management plan
D.lessons learned documentation
单项选择题
In quality planning:
A.The primary benefit of meeting quality requirements is the reduced expense associated with project quality management activitie
B.Cost-benefits tradeoffs must be considere
C.The primary cost of meeting quality requirements is increased rewor
D.Benefits cannot be evaluated in relation to cost
相关试题
  • A metric is an operational definiti...
  • An early version of one of W. Ed...
  • You are a project manager for resi...
  • A project team is in the design s...
  • You are trying to determine what c...