A project team is in the design stage of a new mountain bike prototype. The team is in the process of identifying which type of frame and material will provide high performance at a low cost. Which of the following is the MOST likely technique used to determine these variables
A) Benefit/cost analysis. B) Ishikawa diagram. C) Design of experiments. D) System flow chart.