单项选择题

In your project, you are in the process of determining whether the activities being done as part of your project comply with organizational and project policies. This will be done as part of ______ .

A) inspection
B) quality audit
C) quality improvement
D) trend analysis
<上一题 目录 下一题>
热门 试题

单项选择题
You are the project manager for a manufacturing company involved with making components for Internal Combustion Engines required for the automobile industry. In the past couple of days, there have been too many defects, and you would like to find out whether unusual events are occurring in your manufacturing process whose causes must be identified and corrected. For this purpose, you should use ______ .
A) inspection
B) Pareto charts
C) statistical sampling
D) control charts
单项选择题
A team member notices the project manager that a quality measurement for the project can not be met. What should the project manager do
A) Notify management.
B) Hold a team meeting.
C) Look for alternative ways to meet the quality level.
D) Ask management tp come up with options.