A precision description of a deliverable is called a ______ .
A.Specification
B.Baseline
C.Work package
D.Work breakdown structure element
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
The decomposition process is a technique used to construct a ______ .
A.precedence network
B.critical path method diagram
C.variance analysis
D.work breakdown structure
点击查看答案&解析
单项选择题
An output of scope definition is ______ .
A.work breakdown structure (WB
B.resource breakdown structure (RB
C.project scope statement
D.schedule delays control plan
点击查看答案&解析