单项选择题

When there is uncertainty associated with one or more aspects of the project.one of the first steps to take is to______.

A.revise project plan
B.conduct a risk benefit analysis
C.conduct a needs analysis
D.increase the estimated cost of the project
<上一题 目录 下一题>
热门 试题

单项选择题
As part of risk management process,you just created an overall risk ranking of the project,created list of prioritized risks,identified which risks need additional analysis and determined trends in risk analysis results.What should you do next
A.Analyze the effect of risk events and assign a numerical rating to those risk
B.Create a list of identified risk
C.Determine the fundamental conditions or events that may give rise to identified risk(root causes of ri
D.Note down the list of potential responses to the risk
单项选择题
In your project,there is:25% probability for $25000 profit.50% probability for $40000 profit,25% probability for $100000 profit.What is the expected profit in your project
A.$40000.
B.$50000.
C.$51250.
D.$53750.
相关试题
  • The probability of failure for a p...
  • You are beginning a new project th...
  • You had budgeted $200000 in ...
  • In your project,you have identifed...
  • You are the project manager in an...