单项选择题

在项目财务评价中,若某一方案可行,则( )。

A.P<SUB>t</SUB><P<SUB>c</SUB>,FNPV>0,FIRR>i<SUB>c</SUB>
B.P<SUB>t</SUB><P<SUB>c</SUB>,FNPV<0,FIRR<i<SUB>c</SUB>
C.P<SUB>t</SUB>>P<SUB>c</SUB>,FNPV>0,FIRR<i<SUB>c</SUB>
D.P<SUB>t</SUB>>P<SUB>c</SUB>,FNPV<0,FIRR<i<SUB>c</SUB>