单项选择题

() is the sum of all budgets established for the work to be performed.

A.CPI
B.BAC
C.SPI
D.EAC

<上一题 目录 下一题>
热门 试题

单项选择题
In project management and systems engineering, () is a deliverable-oriented breakdown of a project into smaller components. It is a key project deliverable that organizes the team's work into manageable sections.

A.RBS
B.PBS
C.GBS
D.WBS

单项选择题
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. () process does not belong to Project Integration Management.

A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project