单项选择题

()is one ofthe quality planning outputs.

A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist

<上一题 目录 下一题>
热门 试题

单项选择题
The inputs of developing project management plan do not include().

A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from plamung processes

单项选择题
Which of the following statement related to PMO is not correct?()

A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO. C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.