某工程建设项目中各工序历时如下表所示,则本项目最快完成时间为()(1)周。同时,通过()(2)可以缩短项目工期。

空白(1)处应选择()

A.7 
B.9 
C.12 
D.13

<上一题 目录 下一题>
热门 试题

单项选择题
Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.()is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

A.Cost-Benefit analysis
B.Control charts
C.Quality function deployment
D.Cost of quality analysis

单项选择题
Perform Quality Control is the process of monitoring and recording results of executing the Quality Plan activities to assess performance and recommend necessary changes. ()are the techniques and tools in performing quality control. ①Statistical sampling ②Run chart ③Control charts ④Critical Path Method ⑤Pareto chart ⑥Cause and effect diagrams

A.①②③④
B.②③④⑤
C.①②③⑤⑥
D.①③④⑤⑥