单项选择题

The auditing function that provides feedback about the quality of output is referred to as ().

A.quality control
B.quality planning
C.quality assurance
D.quality improvement

<上一题 目录 下一题>
热门 试题

单项选择题
The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by-overlapping project activities. This approach is known as ().

A.balance engjneering
B.fast-tracking
C.leveling
D.crashing

单项选择题
In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.

A.Activity list
B.Work Breakdown Structures
C.Activity Attributes
D.Milestone Lists