单项选择题

Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and()

A、fast tracking
B、what-if scenario analysis
C、resource leveling
D、critical chain method