单项选择题

某单代号网络计划中,工作N与其紧后工作H和M的时间间隔分别为5周和3周,工H和M的总时差分别为2周和6周,则工作N的总时差是()周。

A.3
B.5
C.7
D.9
<上一题 目录 下一题>
热门 试题

未分类题
June 15,2000Dear Sir,Your shipment of twelve thousand 'Smart' watches was received by our company this morning. However, we wish to make a number of complaints concerning the serious delay in delivery and your failure to carry out our instructions with regard to this order. Late delivery of the goods has caused us to disappoint several of our most valued customers.The second complaint concerns the mismatch in colour between the watches we ordered and those delivereD.As a result of the above problems, therefore, we feel that the most suitable course of action is to return to you unpaid any of the goods considered unsatisfactory.We look forward to your prompt reply.Yours sincerely,Mark SwiftManaging Director,Johnson & Sons LtD.This is a letter ofA.introduction.B.apology.C.complaint.D.recommendation.
A.The
B.
As
C.
We
D.
E.
This
F.introduction.
B.apology.
C.complaint.
单项选择题
共用题干某建筑工程公司最近几年的承包额如下表所示。根据题意,回答下列问题:
A.30500
B.30894
C.31100
D.31500
相关试题
  • 某市邮电局主要从事报刊发行业务,同时兼营...
  • 听力原文:M: My teacher scolded me...
  • 共用题干某工程项目的进度计划如下面双代号...
  • 共用题干某工程项目的进度计划如下面双代号...
  • 共用题干某工程项目的进度计划如下面双代号...